Production Records

Secondary battery’ active-material manufacturing facility

  • 01.

    Design and manufacture of powder equipment

  • 02.

    Design and manufacture of conveying equipment

  • 03.

    Roller Hearth Kiln installation, commissioning

Secondary Battery Automation Roller Hearth Kiln & Transfer Equipment

HISTORY
2020
  • Installation and production of 4-stage 4-row kiln transfer device
2019
  • Installation and production of 4-stage 4-row kiln transfer device
2018
  • Logistics line improvement project (CAM2 ~ CAM4 Line)
  • Production and installation of CAM4 Auger Feeder
  • Design and manufacture of CAM4 kiln transfer device
  • Auger Feeder (filler) production (exported to China)
  • Pilot Line Filling Equipment Manufacturing and Installation
  • Installation and production of transport equipment for 4-stage 4-row atmosphere kiln
  • Installation and production of transport equipment for 6-stage, 4-row atmosphere kiln
2017
  • Installation and production of transport equipment for 4-stage 4-row type kiln
  • Design and manufacture of transport equipment for 2-stage 4-row type kiln
  • Design and manufacture of transport equipment for 2-stage 4-row type kiln
2016
  • AtmosphereRHK Line device and control design production
2015
  • Catalyst RHK raw material recovery device and transfer line installation & manufacturing
  • Auger Feeder
2014
  • RHK Line device and control design & production (exported to Japan)
  • RHK Line device and control design & production (exported to USA)
2013
  • RHK Line device and control design production (2Line)
2012
  • RHK Line device and control design production (8Line)
  • RHK Line device and control design production (2Line)
  • RHK Line device and control design production
2011
  • RHK Line device and control design production
2010
  • RHK Line device and control design production

Secondary Battery Automation Powder Equipment

HISTORY
2020
  • Grinding process and packaging process control equipment (2Line)
2019
  • Manufacture and installation of crushing process & packaging process machine (1Line)
  • Manufacturing and installation of raw material input & mixing process machines (1Line)
  • Roll Mill (coarse grinding) production and installation
2018
  • Weighing & transfer line improvement and installation work (4Line)
  • ACM dust collection tank improvement work
  • Roll Mill (coarse grinding) production and installation
2017
  • Manufacture of crushing & mixing packaging equipment
2016
  • Packaging process design and manufacturing installation (2Line)
  • Design, manufacture and installation of raw material input & mixing process (2Line)
  • Roll Mill (coarse grinding) equipment manufacturing
2015
  • RHK Line device and control design production & installation
2014
  • Additive Mixer
  • Roll Mill (Grinder)
2013
  • Precursor production process design & production
2012
  • Surface Treatment (Coating) Line Design, Manufacturing, and Installation (3Line)
  • Grinding & packaging process design, manufacturing, and installation (2Line)
  • Raw material input& mixing processdesign, manufacturing, and installation (2Line)
2010~11
  • Grinding and packaging process (10Line)
  • Raw material input and mixing process (10Line)